Credit: Cadeler

Cadeler Adds Wind Apex to Dogger Bank C Turbine Installation Campaign from 2027

By:Robertha McDonald | Editor

5 November 2026

Estimated reading time: 3 minutes

COPENHAGEN, November 5, 2026 – Offshore wind installation contractor Cadeler has secured a firm contract to deploy its newbuild vessel Wind Apex at the 1.2 GW Dogger Bank C offshore wind project in the United Kingdom, adding specialist installation capacity as construction progresses on the 3.6 GW development.

The vessel is scheduled to begin operations in the third quarter of 2027, marking its first commercial assignment following delivery from the shipyard.

Under the agreement, Wind Apex will work alongside the project’s existing installation vessel to support the transportation and installation of 87 offshore wind turbines. The additional capacity is intended to strengthen installation operations and support the construction schedule.

Cadeler has not disclosed the contract value or the expected duration of the vessel’s deployment.

Additional Vessel Capacity for 87 Turbines

Dogger Bank C represents the final 1.2 GW phase of the wider Dogger Bank Wind Farm, located approximately 130 kilometres off England’s northeast coast.

The development consists of three equally sized phases, Dogger Bank A, B and C, with a combined planned generating capacity of 3.6 GW. Once fully operational, the wind farm is expected to produce enough renewable electricity to supply approximately six million UK homes annually.

The addition of Wind Apex provides further installation capacity during a construction programme involving some of the largest offshore wind turbines currently being deployed.

The vessel will also be available for assignments across the remaining phases of Dogger Bank, giving the project additional flexibility in allocating installation resources.

For offshore construction logistics, securing vessel availability is an important part of project scheduling. Turbine installation requires coordination between component deliveries, port operations, offshore transportation and suitable weather conditions.

Additional vessel capacity can help contractors manage these activities while reducing reliance on a single installation asset.

Wind Apex Begins First Commercial Deployment

Wind Apex is the third vessel in Cadeler’s A class series, following Wind Ally and Wind Ace.

The vessels are designed for both offshore wind foundation installation and turbine installation, combining substantial deck loading capacity with high capacity lifting equipment.

Their design allows operators to handle larger turbine components and foundations as offshore wind developments move towards increasingly demanding installation requirements.

Mikkel Gleerup, Chief Executive Officer of Cadeler, said the contract reflects the company’s established relationships with major offshore wind developers.

“Dogger Bank is one of the world’s most ambitious offshore wind developments, and we are proud to support its delivery,” Gleerup said.

“The campaign will also mark the first deployment of Wind Apex, and we look forward to seeing her begin operations on a project of this scale.”

Construction Partners Secure Installation Resources

Dogger Bank Wind Farm is owned by SSE with a 40% stake, Equinor with 40%, and Vårgrønn with the remaining 20%.

SSE is responsible for development and construction, while Equinor will operate the completed wind farm throughout its expected operational life of approximately 35 years.

Alan Borland, Turbine Director at Dogger Bank Wind Farm, said securing additional specialist vessel capacity represents another step towards completing the development.

“Wind Apex will join the campaign as an additional turbine installation vessel, working alongside the project’s existing installation vessel to safely and efficiently install Dogger Bank C’s 87 turbines and support the completion of the remaining phases of the project,” Borland said.

The agreement extends Cadeler’s relationship with SSE following earlier work on the Beatrice and Seagreen offshore wind projects in the UK.

Cadeler is also contracted to support the Equinor partnered Bałtyk 2 and Bałtyk 3 offshore wind developments in Poland.


DISCLAIMER: “Breakbulk.News publishes editorial content, including news, features and press releases supplied by third‑party companies, institutions and PR agencies. Third parties who submit material to us are solely responsible for ensuring that all text, images, logos and other content they provide are accurate and that they hold all necessary rights, licences and permissions for news use. By submitting content to Breakbulk.News, contributors represent and warrant that their material does not infringe the rights (including copyright and related rights) of any third party and agree to indemnify Breakbulk.News respecting any claims arising from their submissions. human-edited, AI-assist. If you believe any content on our site infringes your rights, please contact us at info@breakbulk.news with full details and we will investigate promptly. Breakbulk.News is a Trademark of Breakbulk News & Media B.V. in The Netherlands.”