Dachser transports Breakbulk from Brazil to Mexico

Dachser USA, a subsidiary of global logistics provider Dachser, in collaboration with Dachser Mexico and Dachser Brazil, transported 138 tonnes of oversized automotive manufacturing machinery from Jundai, Brazil to Silao, Mexico.

Here’s the full project story:

The customer needed Dachser to transport an oversized compressor machine, which alone weighed 125 tonnes, as well as an additional 14 pieces of varying sizes of accessories from Jundiai, Brazil to Silao, Mexico aiming for arrival in early May.

One of the initial challenges was that the equipment to be shipped was located in an active factory in Jundiai, Brazil, and it was situated within an 18-foot concrete pit. Upon removal from the pit, the machinery needed to be disassembled into 14 pieces of varying size, totaling 138 tonnes. The intricacies of removing the machinery from the plant in Brazil would impact the final timing of the final shipment arrival date.

From the plant, the heavy-lift cargo moved via multiaxel platform trailer through the streets of Brazil following pre-approved routes toward the Port of Santos. Due to COVID-19, there were no police escorts and the cargo could only move during the hours of 11 p.m. to 6 a.m. The 98-mile trip from Jundiai to the Port of Santos took seven days.

blank

Both Ro-Ro and Breakbulk services were considered, but following a thorough analysis of cost, transit time and, most importantly, the safe transport of the cargo, Dachser concluded that a Bulkbreak solution would be the optimal approach, providing the shipper flexibility in loading, storage and unloading, while maintaining efficiency to meet the cost and shipment deadlines.

CMA-CGM was selected for the sea portion of the transport, which, given the timeline, presented its own set of obstacles requiring innovative solutions. Working with CMA-CGM, the Dachser Brazil team needed to determine which type of ocean vessel would be most appropriate for shipping and storing the bulky equipment. Ultimately, it was determined that the most efficient and timely option was to secure a containership.

blank

CMA-CGM agreed to store the cargo in the belly of the ship on flat rack containers and a custom-built platform that would protect the integrity of the equipment and distribute the cargo weight evenly. Prior to arrival at the Port of Santos Brazil, the Dachser Brazil team was charged with developing a solution to load the heavy cargo without conflicting with the Gantry cranes at the terminal. The team arranged for a Floating Crane, a mobile crane that is situated in the water on a barge, which enabled the crew to load on the opposite side of the ship, avoiding the Gantry cranes. This required good weather and precise disbursement of the weight throughout the lifting process.

The cargo was at sea for 30 days, arriving on Sunday, May 3rd, which was the end of a Mexican holiday weekend. The Dachser Mexico team’s well-orchestrated plans ensured the holiday did not slow down the process. The cargo was offloaded directly from the ship to a Modular truck that was waiting alongside the vessel for the oversized cargo. Customs clearance occurred the following day.

blank

Similar to the road transport challenges in Brazil, the emergence of COVID-19 added extra layers of precaution as the cargo moved from the port to the manufacturing facility. While the pre-approved routes along country roads were cleared for the oversized load, the road transport schedule was impacted by some temporary road closures, specific travel hours and lack of local law enforcement escorts. The 436-mile trip from the Port of Veracruz to the customer’s plant in Silao took three days.

Print Friendly, PDF & Email

“Disclaimer: “Breakbulk News & Media BV (Breakbulk.News) assumes no responsibility or liability for any errors or omissions in the content of articles published. The information and or article contained in these articles is provided on an “as is” basis with no guarantees of completeness, accuracy, usefulness or timeliness…”