Pioneering Spirit removes third platform from Brent field

Pioneering Spirit has completed a single-lift removal of Shell UK’s 17,000-tonne Brent Alpha platform from the North Sea, its first decommissioning job of the summer.

Allsea’s Pioneering Spirit will now deliver the 44-year old structure to Able UK’s Teesside decommissioning yard in North East England for dismantling and recycling.

The removal of Alpha is the first offshore lift to utilise our in-house developed “horseshoes”, connection tools that clamp around pre-installed lift points (bearing brackets) mounted on the upper sections of the jacket’s legs.

The Brent Alpha topsides removal project involves engineering, preparation, removal and disposal of the 94 m tall, 52 m wide structure. As with the two previous Brent jobs, Pioneering Spirit will transport the Alpha topsides to a nearshore location off the Hartlepool coastline, where it will be transferred to Allseas’ cargo barge Iron Lady for the final leg of its journey by towage up the Seaton Channel and load-in to the quay at Able UK.

blank
Print Friendly, PDF & Email

“Disclaimer: “Breakbulk News & Media BV (Breakbulk.News) assumes no responsibility or liability for any errors or omissions in the content of articles published. The information and or article contained in these articles is provided on an “as is” basis with no guarantees of completeness, accuracy, usefulness or timeliness…”