Bolloré Logistics China handled six jack-up barges from China to West Africa on behalf of its customer Process Systems, a leading company in the process control industry.

The heavy weight and large size of jack-up barges posed challenges to the Industrial Projects’ teams. Measuring 19 x 19 x 4 metres in size and weighing 190 tonnes each, the jack-up barges reach a total 9,200 cbm (equivalent of 370 TEUs) and 1,135 tonnes.

These heavy lift cargos needed to be transferred from Rushan City, where the factory Fajun Industrial Process and Equipment (FIPE) is located, to Qingdao Port by barge, loaded onto the Mother Vessel at Qingdao Port, and then shipped to West Africa.

To avoid expensive vertical lifting by using a floating crane, Bolloré Logistics decided to shift the cargos horizontally by using the hydraulic system of the self-propelled modular trailers (SPMT). The jack-up barges were standing on elephant legs of 1.8m in height. The teams have been obliged to jack down the jack-up barges from 1.8 metres to 1 metres to perform the transfer from FIPE jetty to the barge.

Before the transfer, Bolloré Logistics finished SPMT assembling and testing at FIPE in advance. After cargo pre-loading survey and supervision by a third-party marine surveyor and close collaboration with each party, these cargos were then transferred in two batches from Rushan to Qingdao Port.

Due to the draft restrictions of minimum two metres during low tide and maximum four metres during high tide, not every barge was able to berth at the factory jetty. The time window to transfer the cargos from the factory to the barge was very important.

To optimise the cost, initially the second batch of three jack-up barges were supposed to be directly transfer to the Mother Vessel. The operation scenario was changed since the bad weather conditions delayed the Mother Vessel arrival at Qingdao Port. Bolloré Logistics has tackled this challenge with a result-driven mindset and efficient solution.

To transfer the jack-up barges to the mother vessel at Qingdao port, Bolloré Logistics has chartered a heavy lift vessel equipped with two gears with 200 tonnes lifting capacity each. The combinable lifting capacity reaching to 400 tonnes in maximum.

In response to these major challenges, Bolloré Logistics’ expert team demonstrated high level of agility, flexibility, adaptability and team spirit, making the whole operation a real success. The operation was completed in March 2021 at the satisfaction of the customer who was delighted with the work done and the efficiency of the service offered.

Print Friendly, PDF & Email

“Disclaimer: “Breakbulk News & Media BV (Breakbulk.News) assumes no responsibility or liability for any errors or omissions in the content of articles published. The information and or article contained in these articles is provided on an “as is” basis with no guarantees of completeness, accuracy, usefulness or timeliness…”