You are here
Home | Logistics | Lifting | Video: Mammoet Makes Historic Bridge Lift

Video: Mammoet Makes Historic Bridge Lift

Mammoet and Flatiron Construction have successfully completed the main span float and lift of the Wellsburg Bridge which connects Wellsburg, West Virginia and Brilliant, Ohio. History was made on the Ohio River during the Wellsburg Bridge project as floating a bridge had never been done before in West Virginia.

Upon completion, the tied-arch bridge will significantly reduce travel time between the two communities, aiding in improved local commerce.

Mammoet’s proposed technical solution utilized its Mega Jack system to jack-up and install the Wellsburg Bridge, weighing 3,870t (8540 kips or 8.5 million lbs.). The overall length of the bridge spanned more than 252 meters (830 ft.) the length of more than two American Football fields.

Mammoet’s Mega Jack solution provided the least disturbance for ships on the river as the work could be completed in a maximum of two days. An alternative strand jacking method would have the bridge hanging on strand jacks for at least two weeks.

Flatiron Construction opted for using Mega Jacks due to increased efficiency, reduced disturbance, and a more controlled method that offered a higher level of safety. This was the first time the Mega Jack 5200 system was used on a barge, and the first time the system of this type and capacity was used in the USA.

Mammoet mobilized eight Mega Jack 5200 towers and eight 500-tonne strand jacks and installed the equipment onto four prepared barges in New Orleans, Louisiana, and began function testing of the system. Flatiron Construction floated the barges to Wellsburg, West Virginia where Mammoet then took over the load of the bridge on its Mega Jack system.

Mammoet jacked up the bridge with a total of six jacking beam layers and their client executed the float in operation. Once positioned next to the bridge piers, Mammoet jacked up the bridge again in order for the bridge to be floated between the piers and over the bridge bearings and the approach girder.

Mammoet’s tool kit consisted of a total of 18 jacking beam layers to cover all possible water levels during execution. In the end, the load was jacked up a total of 15 jacking beam layers on six towers and 16 jacking beam layers on the other two towers to account for variances in the interface beams which were provided by others.

Next, the jack-down operation began to precisely position the bridge on its bearings and to allow the barges to be floated away. Mammoet’s technical solution provided advantages, such as allowing the bridge to be built at ground level and allowing it to be safely jacked-up while loaded on the barge – bringing the bridge to the elevation required for installation. Therefore, all jacking works could be executed at a lower level and reduce working at height.

Forecasted windy weather conditions prompted a decision to expedite the schedule and complete the full float-in and jacking operation in one day instead of two as originally scheduled. With safety as highest priority, Mammoet skillfully executed the scope of work ahead of schedule in one day without incident. Mammoet used its global engineering resources and the world’s largest heavy lift equipment fleet to make sure it could deliver the right expertise, in the right place, at the right time.

Print Friendly, PDF & Email

“Disclaimer: “Breakbulk News & Media BV (Breakbulk.News) assumes no responsibility or liability for any errors or omissions in the content of articles published. The information and or article contained in these articles is provided on an “as is” basis with no guarantees of completeness, accuracy, usefulness or timeliness…”

blank
blank
blank
blank
blank
Top